PRODUCTION FACILITIES
NorSun
operates state-of-the-art manufacturing facilities with further expansion plans.
NORSUN ÅRDAL (Norway)
- Production of monocrystalline ingots and wafers
- Current production capacity in excess of 250 MWp
- 70 pullers and 16 wire saws
- 233 employees
- Construction started in June 2007 and commercial production began in Q2 2008
Monocrystalline ingot at NorSun Årdal:
NEW VANTAA (Finland)
- Production of monocrystalline ingots
- Current production capacity in excess of 30 MWp
- 10 crystal pullers in operation
- Okmetic personnel only
- The plant is owned and operated by Okmetic, while crystal pulling equipment is owned by NorSun
- Production began in Q4 2007
NORSUN JURONG (Singapore)
- Production of mono-crystalline ingots, wafers
- Expected capacity of over 500 MWp in phase 1 in 2013
- The production facilities are planned in two phases:
- Phase 1: planned capacity of approximately 100 pullers and corresponding sawing capacity
- Phase 2: the site has room for doubling the phase 1 capacity
- Approximately 310 employees when fully developed in phase 1
- Construction started in August 2008 (postponed in November 2008)
Planning NorSun Singapore: